River Restoration & Enhancement Case Studies

Cain Bio-Engineering have undertaken numerous river restoration, enhancement, erosion control and river management projects over the last 30 years. In our river case studies section you will find more information, photos, videos and documentation about some of our favourite projects.

Rock ramp creation – Pillhill Brook

by Matthew Irvine on February 19, 2015

Cain Bio-Engineering recently completed some remedial works to an overspill weir serving a winterbourne on the Pillhill Brook near Andover.

Read Full Article

Tidal embankment stabilisation – River Rother at Rye

by Matthew Irvine on January 16, 2015

Cain Bio-Engineering on behalf of the Environment Agency have recently completed 260 metres of bank stabilisation works on the River Rother at Rye over three separate locations.

The work involved driving large chestnut stakes into the eroded banks and installing hazel faggot lattices between these stakes to hold new sediment deposits in place. This allows collapsed areas of bank to recover and stabilise. Read Full Article

Upavon Restoration works with the Environment Agency

by Matthew Irvine on January 14, 2015

Cain Bio-engineering have recently completed restoration works on the upper section of the River Avon at Upavon in association with the Environment Agency.

This section of the River Avon has suffered from over widening and deepening due to past dredging, resulting in a loss of marginal habitat and disconnection with the floodplain. The restoration works included the removal of an old weir , marginal habitat creation, bank regrading and floodplain re-connection. Read Full Article

Bournemouth Stour – New revetment created

by Matthew Irvine on May 23, 2014

Cain Bioengineering have successfully completed the creation of a new revetment and bank stabilisation project for Bournemouth District Council on the River Stour.

Read Full Article

River Case Study: Profits Wood

by Jake Dew on February 17, 2014

Project type:  Erosion Control
Location:  Chandler’s Ford, Hampshire
Length:  55m of new channel
River:  Chandler’s Ford stream
Client:  The Woodland Trust
Installation date:  2009

Project Brief

Erosion of this small headwater channel during high flows was increasing the risk of bank failure on the steep outside meanders and threatening to cause loss of land in nearby houses.

Cain Bio-Engineering designed and built a new channel through the adjacent ancient woodland, diverting the stream away from the housing.  The old channel course was in filled with excavated material from the new channel and the upstream and downstream extents protected using retained rock armor.  The new channel course was carefully selected to reduce the amount of mature trees removed. Imported gravel was used to create spawning habitat for Salmonids and LWD installed to provide additional habitat variation.

Read Full Article

River Case Study: Thames Valley Park

by Jake Dew on February 17, 2014

Project type:  Erosion Control
Location:  Thames Valley Park, Reading
Length: 60m
River:  Thames
Client:  GVA Grimley
Installation date: June 2012

Project Brief

The retained river bank fronting of the Wokingham Waterside Centre in Thames Valley Park, Reading had eroded and was de-constructing due to a combination of wave action, foot traffic and wildfowl.

Cain Bio Engineering designed and installed a new hard wearing bank front using timber sleepers and gravel.

Read Full Article

River Case Study: Kennet Wasing

by Matthew Irvine on December 10, 2013

Project type: Erosion Control
Location:  Wasing Estate, Berkshire
Length: 120m
River:  Kennet
Client:  Wasing Estate
Installation date:  May 2011

Project Brief

The river at this location runs between two lakes with just 8.5 metres between the banks of the river and the banks of the lake.

It was only a matter of time before the narrow track which separates the River Kennet from Oxlease Lake was breached. This would have had significant access, as well as environmental and financial implications if it was left unchecked.

Read Full Article

River Case Study: Ravensbury Park Weir Removal

by Jake Dew on December 19, 2012

Project type:  Weir removal and habitat restoration
Location:  Ravensbury Park, Morden, London
Length: 30m
River:  Wandle
Client:  The Wandle Trust
Installation date:  September 2012

Project Brief

A stepped concrete weir on a side channel of the River Wandle created a complete barrier to fish passage and a Water Framework Directive (WFD) failure. The weir also led to sluggish upstream river speeds and the silting up of the channel limiting its habitat diversity.

Cain Bio-Engineering reconnected the river by breaking out the concrete weir and stabilising the bed using sweet chestnut post flow attenuators and locally sourced large gravels.

 We also replaced the dilapidated oak boarding with a a geotextile revetment which is designed to fully vegetate.

Read Full Article

River Case Study: A36 Southington Farm

by Jake Dew on July 27, 2012

Project type:  Erosion Control
Location:  Stapleford, Salisbury, Wiltshire
Length:  55m of geotextile revetment
River:  Wylye SSSI
Client:  Balfour Beatty, Mott MacDonald, Highways Agency
Installation date:  October 2011

Project Brief

This project is located on the River Wylye adjacent to the A36 west-bound carriageway.  River bank erosion was threatening the stability of the highway.

Cain Bio-Engineering Ltd designed and constructed a geotextile structure to re-claim and stabilise the entire length of affected left bank downstream of the bridge.

Winner of Chartered Institution of Highways and Transportation Award for Sustainability 2012

Read Full Article

Project type: Mill Leat Bypass
Location: Arborfield
Length: 200m of new bypass channel
River: Loddon
Client: Environment Agency
Installation date: 2011

Project Brief

On the River Lodden at Arborfield, historic mill and weir structures prevented fish passage, and had impounded the river for 4km upstream.

 A combination of civil engineering and soft engineering techniques were used to design and build a 200m weir bypass channel to reconnect 25km of the River Loddon.

Runner up prize in the Wild Trout Trust river restoration competition 2011 (professional category)

Delegates visiting the river Loddon site Delegates visiting the site

Read Full Article