Case Study - Rivers - Charmouth Sewage Treatment Works


Project: Thames Henley Management College

Project Location: Henley on Thames

River System: River Thames

Client: 


Date of Installation: 2005
 






Project Brief

To:
 

  • Provide sustainable soft engineered bank protection and arrest the severe undercutting of an original dry concrete bank.
  • The design must take into consideration longevity, bio-diversity and must be designed in such a way that it is in keeping with HMC prestigious history and surroundings.
     

Solution


Cain Bio-Engineering Ltd designed and installed a robust marginal vegetated mattress along the entire river bank at HMC.

Constructed of hardwood posts with a woven hazel face, the marginal mattress is designed to withstand and dissipate the wave action caused by boat traffic.

This cost effective, soft engineered approach uses the marginal wetland vegetation as a way of dissipating boat bow wave energy, whilst at the same time providing habitats for aquatic animals and taking into consideration the aesthetics of the features in its prestigious surroundings


December 2005- Historic bank revetments undermined by wave action and Sgnal Crayfish burrowing


September 2006- following installation of a reinforced vegetated marginal mattress